The Northfield Township Road District lets construction contracts by sealed, competitive bid. Every step is public. This page and the project pages below hold the record for each bid letting, so residents, bidders and reporters can see what happened without filing a Freedom of Information Act request.
Current and recent bid lettings
| Project | Number | Bid opening | Status |
|---|---|---|---|
| Sanders Road Sidewalk Project 2026 | NTRD-2026-05 | Friday, September 25, 2026, 11:00 a.m. | Open — bids due at opening |
| Road District Garage — Triple Basin Project | NTRD-2026-02 | August 25, 2026 | Bids under review — no award made |
| Citation Lake / Northbrook West Stormwater Improvements — Phase 1 | NTRD-2025-CITLAKE-P1 | 2025 | Awarded to DiMeo Brothers, Inc. |
How a bid letting works
- Advertise. Contracts over $30,000 for construction, materials or equipment (other than professional services) are advertised in a local newspaper at least 10 days before bids are opened (605 ILCS 5/6-201.7, as amended by Public Act 103-0125, effective June 30, 2023).
- Distribute plans. Bidders get plans and specifications through DemandStar, the District’s bid distribution service. Every firm that takes a set is recorded on the plan holders list.
- Answer questions. Questions are answered in writing. Any change to the bid documents is issued to every plan holder as a numbered addendum.
- Receive sealed bids. Bids are time-stamped when received and stay sealed until the announced opening time. Late bids are returned unopened.
- Open bids in public. At the announced time and place, each bid is opened and read aloud: bidder name, total bid, bid security and addenda acknowledged. Anyone may attend. The opening follows a written procedure and script, posted on each project page.
- Review. The project engineer checks every bid for math errors and responsiveness and prepares a certified bid tabulation.
- Award. The contract goes to the lowest responsible bidder. The award action, contract, bonds and insurance are posted to the project page.
- Build. Change orders, pay applications and final acceptance are added to the project page as the work proceeds.
What is posted, and when
| Stage | Records posted to the project page |
|---|---|
| Before the opening | Invitation to Bid and newspaper notice, addenda, questions and answers, plan holders list |
| At the opening | Bid opening procedure and script, sign-in sheet, Public Bid Opening Record (bidders and amounts as read aloud) |
| After review | Engineer’s certified bid tabulation and recommendation |
| After award | Award action, Notice of Award, executed contract, bonds and certificates of insurance |
| During construction | Notice to Proceed, change orders, pay applications, final acceptance |
Why some documents appear later: Under the Illinois Freedom of Information Act, sealed bids and bid proposals are exempt from release until an award or final selection is made (5 ILCS 140/7(1)(h)). The names and totals read aloud at a public opening are public from that moment and are posted with the opening record.